Project
Schedule
The
concept planning process began in February of 2006 with the selection
of the consulting team to assist with the project. The effort is
expected to be completed by May, 2007. Major steps and milestones
in the process include the following:
May,
2006 - Establish the Citizen Advisory Committee (CAC) and
Technical Advisory Committee (TAC)
May
to June, 2006 – Prepare the Public Involvement Plan,
Preliminary Goals and Committee Guidelines
June
to August, 2006 – Establish the Existing Conditions,
Opportunities and Constraints
July,
2006 – Conduct the Market Focus Group
August,
2006 - Conduct the Sustainability Focus Group and hold
the first Open House
August
to September, 2006 – Review Project Goals and Prepare
Evaluation Criteria
September
to October, 2006 – Prepare Alternative Concept Plans,
Infrastructure Plans, Cost Estimates and Fiscal Impacts
October,
2006 - Conduct the Design Workshop
October,
2006 to January, 2007 – Prepare a Draft Concept Plan
February,
2007 - Conduct the second Open House
March,
2007 to May, 2007 – Prepare the Final Concept Plan,
Comprehensive Plan and Code Amendments and Adoption Process
View
the Beavercreek Road Concept
Plan Work Plan Summary |