Skip to Main Content
Thursday February 9th
  • 2010 Oregon City Slurry Seal Project

  • Type

  • Street
  • Status

  • Completed
  • Budget

  • $154,567.70 (Blackline, Inc.)
  • Dates

  • Construction: Sept. 20, 2010 - Oct. 11th, 2010
  • Alerts and Updates

  • October 8:  Slurry seals for those streets rescheduled for Thursday were partially completed with the following remaining streets to be completed on Monday, October 11, 2010:

     

    Slurry Seal Schedule - Monday, October 11
    STREET FROM TO SQUARE YARDS
    Hein St Highland Dr End (Partial Section not completed 10/7/10 4,741
    Chapin Ct Hein St End 1,037
    Four Oaks St Blue Ridge Dr End 1,768
    Faircrest Dr Chiara Dr Towercrest Dr 2,542
    Chiara Dr Towercrest Dr Spring Valley Dr 2,001
    Westwood Dr Skellenger Way Hartwood Dr 6,846
    Warner Milne Rd Beavercreek Rd Leland/Linn/Warner Parrott Center turn lane only

    October 7:  Slurry seals for those streets originally scheduled to be slurry sealed on Monday, October 4, have been changed to Thursday, October 7, weather permitting.  See updated project schedule below.

     

    September 29 through October 7:  Weather permitting, slurry seal application is expected to occur on these dates.  To find out more about this process, check out our 2010 Slurry Seal Schedule, 2010 Slurry Seal Map, and 2010 Neighborhood Notification Letter below. 

     

    September 2, 2010:  In addition to the slurry seal project, Clackamas County has also applied a "chip seal" on Warner Parrott from South End Road to Mt. Pleasant Elementary School and on Linn Avenue from Warner Milne Road to Holmes Lane.  The County will be applying the fog seal today and striping will be completed over the weekend but done by Sunday. 

      

    July 13, 2010:  Bids were opened at 2:00 p.m.  The apparent low bidder is Blackline, Inc. and the bidders and the bid amounts are as follows:

    Apparent Bid Results
    Bidder Bid Amount
    Blackline, Inc. $154,567.70
    Asphalt Pavement Maintenance $166,588.36
    Intermountain Slurry Seal, Inc. $255,255.00

     

    June 24, 2010:  Project advertised in the Portland Daily Journal of Commerce.  Bids due no later than 2:00 p.m. local time on July 13, 2010.  Work to be done consists of the application of approximately 133,874 square yards of slurry seal material including the street preparation, neighborhood notification, traffic control, material delivery, material application and final project cleanup. 

     

     

  • Project Details

  • Slurry Seal Truck Applying Product

    Annual installation of a slurry seal application on select Oregon City streets to prolong the life of the street. 

    September 29 through October 11, 2010:  Weather permitting, slurry seal application is expected to occur on these dates.  To find out more about this process, check out our links below.