  • 2010 Pavement Rehabilitation Project

  • Type

  • Street
  • Status

  • Archived
  • Budget

  • $492,670.00 (Parker NW Paving Co.)
  • Dates

  • Expected Completion: July 15, 2011
  • Contact:

  • City Project Manager: John Lewis, P.E., Operations Manager, 503.657.8241 or jmlewis@orcity.org and Erik Wahrgren, P.E., Project Engineer at 503.496.1510 or ewahrgren@orcity.org

    Engineering Consultant: Ken Valentine and Gary Alfson, 503.221.1131, Harper Houf Peterson Righellis Inc.

  • Alerts and Updates

  • June 9, 2011 - Final construction schedule as submitted by the contractor:

    • 5-23 to 5-27 - Saw cut for added asphalt concrete paving repair, prep and pour new ADA ramp and pad at Hiefield Ct.
    • 5-31 to 6-3 - Prepare manholes, valves, monument boxes, etc., to prepare for milling
    • 6-6 to 6-10 - Excavate and patch 189 sq yds added asphalt concrete pavement repair areas, finish manholes
    • 6-13 to 6-24 - Grinding, paving and striping, rock shoulders
    • 6-27 to 6-30 - Adjust manholes, final cleanup
       

     

  • Project Details

  • Construction of 2010 road overlay project utilizing the Pavement Maintenance Utility Fee collected through the City's utility bill.  Anticipated street sections include:

    2010 Street Work
    Street Beginning End
    Leland Road Warner Milne Road Clairmont Way
    Meyers Road Clairmont Way Frontier Parkway