  • 2010 Waterline Improvements Project

  • Type

  • Water
  • Status

  • Archived
  • Budget

  • Construction: Approx. $375,000
  • Dates

  • Design: May through August, 2010 - Construction September through December, 2010
  • Contact:

  • City Project Manager: John Burrell at 503.496.1556 or jburrell@orcity.org

    Engineering Consultant: Mike Carr, Murray, Smith & Associates, Inc. at 503.225.9010

  • Alerts and Updates

  • September 7, 2010:  Bids were opened with the apparent low bid being submitted by Canby Excavating, Inc.  Bid results are as follows

    BID RESULTS
    BIDDER AMOUNT
    I & E Construction Inc.  $334,804.00
    Canby Excavating  $230,595.50
    Dirt and Aggregate Interchange  $357,747.00
    Moore Excavation, Inc.  $393,350.00
    Ground Hawg Environmental  $288,144.98
    CivilWorks NW, Inc.  $298,270.00
    Jim Smith Excavating, Inc.  $269,410.00
    Dunn Construction Inc.  $338,070.00
    D M Excavating Company, Inc.  $313,620.00
    Paul Lambson Contracting  $257,000.00

      

    August 31, 2010:  Addendum #1 issued. 

    August 26 & 30, 2010:  Invitation to Bid was published in the Portland Daily Journal of Commerce. 

     

  • Project Details

  • Vicinity Map

    2010 capital improvements to Oregon City's water system including constructing approximately 2,300 feet of new 8-inch ductile iron waterline on Eastborne Drive and Chippendale Drive.