  • 2012/2013 Oregon City Roadway Reconstruction Projects

  • Type

  • Construction
  • Status

  • Archived
  • Budget

  • $2M Design and Construction
  • Dates

  • Design January to June, 2012; Construction September to November, 2012
  • Contact:

  • The project manager, John Burrell, can be reached at 503.496.1556 or jburrell@orcity.org.

  • Alerts and Updates

  • Project Details

  • 2012/2013 Oregon City Roadway Reconstruction Projects

     

     

    The project is nearing completion.  Check here for a schedule for the week of November 5, 2012.

     

     

     

     

     

     

     

     

     

    Keep in mind that all work is weather dependent so the schedule will be adjusted accordingly.  Work hours are from 7:00 am to 6:00 pm.

     

    If you live in the vicinity of these streets, please ensure all vehicles and items are off the street to help the work go as quickly as possible.

     

    Week of November 5 (weather dependent):

    Date Street Segment Work
    Thursday, November 8 through Friday, November 9 Barclay Hills Drive Alden St west ~200' to Molalla Ave Sanitary sewer repairs requiring that any device that drains to the sanitary sewer (toilets/showers/sinks/washing machines/dish washers/etc.) not be used at certain times.

     

    Week of October 15 (all tentative):

    Date Street Segment Work
    Tues, Oct 16 Barclay Hills Dr Molalla Ave to Chickaree Dr Digout/Reconstruct Portions of Roadway
      Barclay Hills Dr Molalla Ave to Chickaree Dr Mill/Grind Roadway
    Wed, Oct 17 Barclay Hills Dr Molalla Ave to Chickaree Dr Pave Roadway
      7th St Harrison to Division St Mill/Grind Roadway
      Gaffney Ln Molalla Ave to Berta Mill/Grind Roadway
    Thur, Oct 18 Gaffney Ln Molalla Ave to Berta Pave Roadway
      7th St Harrison St to Division St Pave Roadway
    TBD Hazel St Linn Ave to East Ave  

     

    Week of October 8 (COMPLETE):

    Date Street Segment Work
    Mon, Oct 8 Josephine St Lawton Rd to end Pave Roadway
      Netzel St Lawton Rd to end Pave Roadway
      Division St 7th to 15th St Mill/Grind Roadway
      Holmes Ln Telford Rd to McCarver Ave Digout/Reconstruct Portions of Roadway
    Tue, Oct 9 Holmes Ln Telford Rd to McCarver Ave Mill/Grind Roadway
      S. 2nd St Hwy 99E to High St Mill/Grind Roadway
      Division St 7th to 15th St Pave Roadway
      Pleasant Ave Approx. 424 to 510 Pleasant Ave Digout/Reconstruct Portions of Roadway
    Wed, Oct 10 Pleasant Ave Molalla Ave to Molalla Ave Mill/Grind Roadway
      S. 2nd St Hwy 99E to High St Pave Roadway
      Holmes Ln Telford Rd to McCarver Ave Pave Roadway
           
    Thu, Oct 11 Pleasant Ave Molalla Ave to Molalla Ave Pave Roadway
           
           
           

     

    Week of October 1(COMPLETE):

    Start Date End Date Street Segment
    Mon, Oct 1 Tue, Oct 2 Ogden St Telford Rd to Brighton Ave
    Tue, Oct 2 Wed, Oct 3 Birchwood Dr Warner Parrott Rd to Hazelwood Ave
        Barclay Ave Telford Rd to Cherry Ave

     

    Date Street Segment Work
    Fri, Oct 5 Josephine St Lawton Rd to End Mill/Grind Roadway
    Fri, Oct 5 Netzel St Lawton Rd to End Mill/Grind Roadway

     

    YOUR PMUF AT WORK

     