The City's project manager, Erik Wahrgren, can be reached at ewahrgren@orcity.org or 503.496.1510.
July 2, 2012 - The project updates are as follows:
May 29, 2012 - Bids opened with apparent bid results as follows:
| BIDDER | BID TOTAL |
|---|---|
| Kodiak Pacific Construction | $379,379.00 |
| Nutter Corp. | $456,672.22 |
| PCR Inc. | $510,529.00 |
The Notice of Intent to Award Contract letter has been distributed and the bid tabulation spreadsheet is now available. Bid award is anticipated at the June 6, 2012 meeting of the City Commission.
May 24, 2012 - Addendum 1 issued (also available below).
May 24, 2012 - Illegible pages IL1, TS1, TS2, TS3, TS4, TS5, TS6 and TS7 uploaded. Illegible pages SS1 and SS2 have also been updated and are included in Addendum 1.
May 8, 2012 - Invitation to Bid issued May 8 and May 10, 2012 in the Portland Daily Journal of Commerce. A nonmandatory preconstruction meeting is scheduled for May 17 and bids are due May 29. For specific information, please refer to the Invitation to Bid available below.

The engineering firm of Wallis Engineering PLLC has designed improvements on Beavercreek Road at its intersection with Molalla Avenue. Currently, the west leg of Beavercreek Road at its intersection with Molalla Avenue has three lanes going eastbound: A center left turn lane, a through lane, and a through or right turn lane. This project will include the construction of one additional lane to serve as a dedicated right-turn only lane.
The final configuration will consist of a center left turn lane, two through lanes, and a right turn lane.