Construction Update

Roadway Excavation & Asphalt Cement Paving Operations
Project: Warner Milne Road Improvements Project (Oregon City)
Location: Warner Milne Road from Molalla Avenue to Beavercreek Road
When: Tuesday, July 6, 2010, through Saturday, August 7, 2010
Working Hours: 7:00 AM to 7:00 PM, Monday through Saturday
NOTE:
- The approximate thirty (30) days excavation/paving operations are tentatively scheduled for Tuesday July 6th through Saturday August 7th .
- The paving operations are weather dependent.
- Working hours will be from 7:00 AM to 7:00 PM Monday through Saturday.
Traffic Control:
- During this phase of the project Warner Milne Road will be one way in the westbound direction from Molalla Avenue to Beavercreek Road.
- Warner Milne eastbound traffic will be detoured at Beavercreek Road.
- Access to driveways on Warner Milne Road will be maintained to the maximum extent possible, but will be temporarily disrupted during work immediately adjacent to each driveway.
- Flaggers will be controlling traffic at driveways during the excavation and paving operations.
- Flaggers will also assist with pedestrians access to business and residents.
- Temporary signage showing “ONE WAY” will be placed at each driveway directing traffic in the westbound direction on Warner Milne Road.
Construction Operations:
- Core out existing road structural section south side of Warner Milne.
- Place aggregate base and compact.
- Place asphalt pavement in two lifts with compaction operations between the lifts.
- Core out existing road structural section north side of Warner Milne.
- Place aggregate base and compact.
- Place asphalt pavement in two lifts with compaction operations between the lifts.
- Place asphalt pavement final lift.