  • South End Road Pavement Construction

  • Type

  • Streets
  • Status

  • Completed
  • Budget

  • Not Available
  • Dates

  • August 2009
  • Alerts and Updates

  • Project Details

  • South End Road Pavement Construction

    The City has contracted with Icon Construction to pave a portion of South End Road. This project will include a full width grinding/milling effort with new asphalt being applied after the initial grinding.

     

    This project will begin onTuesday August 18th, continue through Wednesday the 19th and will be completed on Thursday August 20th in the afternoon. Roadway striping and pavement markings will follow soon after the paving is complete.

     

    The project will begin at 7:00am and will generally end at 5:00 pm. Drivers should expect some delay and may want to plan trips around the project site.

     

    Flaggers will maintain ONE lane of travel on South End road and will provide guidenance to assist drivers thru the work site.