Molalla Transmission Main - wifia 3-1 (CI 22-014) 

PROJECT OVERVIEW

This project is a vital long-term investment in the city's water system that will improve reliability, meet peak water demands, support growth, and ensure consistent water delivery by replacing aging infrastructure with a higher-capacity pipeline.


WILL THE ROADWAY BE ADDRESSED?  

The pavement patches are temporary, with permanent paving scheduled for spring 2026.  Why the delay?  Additional pipework still needs to be completed, including mainline extensions on side roads and the installation of new services. Once this work is complete, the pipe then needs to be tested, and any issues fixed before permanent paving can take place. To learn more, read the Project Details below. 

  • Project Type: Water Project (Capital Improvement)
  • Project Total Budget: $ 8,638,000
  • Funding Sources: Water Rates, Water System Development Charges (SDC) and Federal Funding from the Water Infrastructure Innovation Act (WIFIA)
  • Project Location: Holmes Lane from Mountainview Reservoir to Molalla Avenue and Molalla Ave from Holmes Lane to Beavercreek Road. 
  • Neighborhood(s): Hillendale and Elyville
  • Project Dates 
    • Design: July 2023 - December 2024
    • Construction: January 2025 - June 2026
  • Project Manager: Patty Nelson, P.E.

PROJECT UPDATES  

(Updated 12/31/2025)

12/31/25 - This project has completed installation of all mainline water mains and services. 

December's work focused on the 30-inch transmission main located across the City’s Mountainview Reservoir Property, where it will eventually connect to the existing pump station. 

As we begin the new year, crews will prepare to test the newly installed pipe.  Once the pipe has passed all required testing, work will proceed to connect to the existing system serving businesses and homes. More detailed information will be provided in advance, and notices will be issued prior to any anticipated water disruptions. Following successful testing, preparations for permanent pavement restoration can begin, which will provide a smoother driving experience.  This work is weather-dependent, so we are hopeful that mild weather conditions continue. 

  1. 1 a large water main pipe lying in a dirt trench.
  2. 2 30 inch water pipe being lowered into a trench by reservoir
  3. 3 onstruction on a fire hydrant lateral crossing, with a red hydrant standing next to an open, excavat
  1. Patty Nelson

    Senior Project Engineer