linn basin sanitary sewer i & i rehab project 2 (ci 23-002) 

PROJECT OVERVIEW

This project is one of many identified in the Inflow and Infiltration (I & I) Program. Inflow and infiltration are when stormwater and groundwater enter the sanitary sewer system. Through this project, sanitary sewer mains (large publicly owned sewer pipes in the street) will be rehabilitated and repaired as priority repairs due to the current conditions of these systems. Sanitary sewer systems located on the west side of the Promontory (overlooking Waterboard Park - Brighton and Terrace Avenues) and various streets in the vicinity of East Street (below the Promontory) and Pearl Street just west of Molalla Avenue will be addressed. Read more in the Project Details below. 

  • Project Type: Sanitary Sewer
  • Project Total Budget: $5,100,000.00
  • Funding Sources: Sewer Rates
  • Project Location: West side of the Promontory (overlooking Waterboard Park - Brighton and Terrace Avenues), as well as various streets in the vicinity of East Street (below the Promontory), 4th Street (west of Linn Avenue), and Pearl Street (just west of Molalla Avenue).
  • Neighborhood(s): Elyville, Rivercrest
  • Project Dates
    • Design: January 2023 through May 2025
    • Construction: Spring 2026 through October 2026
  • Project Manager: Kenny Cannady-Shultz
  • Moore Excavation, Inc. will be conducting pipe investigations, preparing lateral line plans and obtaining permits necessary to begin the construction work on this project. Construction is expected to being in Spring 2026. 
  • The construction contract was awarded to Moore Excavation, Inc. on October 15, 2025 by the City Commission. 
  1. 1 McLoughlin Basin, Map, Sewer
  2. 2 Lateral Line
  3. 3 Street, Trees
  4. 4 Street, Trees
  1. Kenneth Cannady-Shultz

    Project Engineer